Menahga School construction project waiting on state

Email News Alerts

Menahga School's construction projects are underway but a storm sewer issue has left the locker room addition running behind.

Project manager Nick Ylitalo, with JP Structures, said Monday evening that the existing storm sewer wasn't "jiving" with the mechanical plans so revisions will be required.

Advertisement

"We are currently waiting for a response from the state to determine what an approved alternative will be," he said.

Are you a newspaper subscriber but you don't have a Digital Access account yet? https://secure.forumcomm.com/?publisher_ID=40&event=subscriber/lookup.

You will need your subscription account number and phone number. Not sure if you have an account? Email us at subscriberservices@forumcomm.com and we can help you.

Advertisement
Anna Erickson
Anna Erickson is editor of the Park Rapids Enterprise.
(218) 732-3364
Advertisement