Work on the bridge started too late to complete the project on time. (Sarah Smith / Enterprise)

Liquidated damages go into effect for Hubbard County 39 bridge project

Email

Work on Hubbard County's 39 bridge is behind schedule and the contractor is paying $1,000 a day in liquidated damages.

A detour in the northern part of Hubbard County remains in place.

"They didn't get here soon enough to get started so now they're out of working days," county engineer David Olsonawski said of Duininck Brothers, Inc.

Are you a newspaper subscriber but you don't have a Digital Access account yet? https://secure.forumcomm.com/?publisher_ID=40&event=subscriber/lookup.

You will need your subscription account number and phone number. Not sure if you have an account? Email us at subscriberservices@forumcomm.com and we can help you.

Advertisement
ssmit

Sarah Smith is the outdoors editor. She covers Hubbard County, courts and breaking news.

(218) 732-3364
Advertisement
Advertisement
randomness